摘 要 介绍了在不影响煤矿正常生产,不破坏现有工程和设施的条件下,后期施工煤仓所采用的特殊施工方法和技术措施。
关键词 特定条件 煤仓 施工
Coal Bunker Construction Method under Special Conditions
A construction of coal bunker is a difficult construction project in mine chamber construction.Especially a coal bunker construction conducted when the mine in coal production should not make any failure to the existing project and facilities in order not to influence the normal coal production in the mine.Special construction method and measures should be taken for the bunker construction.This paper introduced a coal bunker constructed between - 550 m Level and - 450 m Level in Xinji No.2 Mine.A pilot bore hole was drilled with a raise boring machine for the coal bunker.Then the pilot bore hole was enlarged step by step with a conventional drilling and blasting method.A on time support system was used for the enlarged coal bunker.The support system was including bolt, wire net and shotcrete.Two coal bunkers were successfully, rapidly and safely constructed in the mine.
1 工程概况
在新集二矿施工的-550 m水平煤仓,净径6m,高23.5 m;-450 m水平煤仓,净径6m,高18m(图1)。两个煤仓的上口均处在宽2.8 m,高2m矩形断面的两个斜巷中;下口给煤机硐室所处的胶带机巷都已安装完胶带机。煤仓施工时,不能影响胶带机的正常运转,不能对胶带机有丝毫损坏,否则将会造成整个矿井停产。

|
图1 煤仓位置示意图 2 施工方案 3 煤仓施工
导井施工,先用反井钻机打导孔,钻透仓底,然后自下而上扩孔,形成导井。由于导井的下方正对胶带,因此,开钻前,在胶带上方约1 m处的巷道两帮各安装6组托盘器,托盘器沿煤仓中心对称布置,间距1.5 m。每组托盘器为两根Ø40 mm、长1.2 m、一头带弯的圆钢,用凿岩机打眼安装,两圆钢间距250~300 mm,其上安设长500 mm的12号矿用工字钢。在两帮对应的托盘器上架设20号工字钢,上铺70 mm厚的木板作为临时操作盘。整个操作盘的所有构件之间都用卡具或铁丝连接牢固。该盘既是换扩孔钻头的操作盘,又是扩孔时岩碴的集承盘。 |

|
图2 -550 m水平煤仓施工布置图 4 结语 作者简介:韩宏斌,工程师,1988年毕业于中国矿业大学建筑系矿建专业,现为新集二矿工程项目部技术主管。地址:江苏省徐州市,邮码:221131。 |
煤炭网版权与免责声明:
凡本网注明"来源:煤炭网www.coal.com.cn "的所有文字、图片和音视频稿件,版权均为"煤炭网www.coal.com.cn "独家所有,任何媒体、网站或个人在转载使用时必须注明"来源:煤炭网www.coal.com.cn ",违反者本网将依法追究责任。
本网转载并注明其他来源的稿件,是本着为读者传递更多信息的目的,并不意味着本网赞同其观点或证实其内容的真实性。其他媒体、网站或个人从本网转载使用时,必须保留本网注明的稿件来源,禁止擅自篡改稿件来源,并自负版权等法律责任。违反者本网也将依法追究责任。 如本网转载稿件涉及版权等问题,请作者在两周内尽快来电或来函联系。
网站技术运营:北京真石数字科技股份有限公司、喀什中煤远大供应链管理有限公司、喀什煤网数字科技有限公司
总部地址:北京市丰台区总部基地航丰路中航荣丰1层
京ICP备18023690号-1 京公网安备 11010602010109号